SCOPE: Luxury student housing apartments with below grade parking
LOCATION: Charleston, SC
GENERAL CONTRACTOR: Armada Hoffler
SITE AND/OR SUB-CONTRACTOR: Lithko Contracting, LLC
Pump company and/or finisher: Concrete Material Placement (CMP)
COMPLETION DATE: Project broke ground in 4Q 2017, mud mat pour 3/7/18. Completed by 2019
PROJECT DESCRIPTION:
Armada Hoffler is an owner/developer for a luxury student housing apartment complex designed to accommodate the vast growing population on the Charleston Peninsula. The project required extra attention as a 1300 cubic yard concrete pour was required to meet the demanding schedule, which was delivered at a rate of 200 cubic yards/hour from Knight’s Spruill Ave Central Mix plant.